What are the permits and timeline for building on a vacant Keys lot?

By Steve Conley

Short Answer

Building on a vacant Keys lot requires a ROGO allocation (2 to 10+ year wait depending on tier), environmental permits from multiple agencies, building permits from Monroe County, and compliance with FEMA elevation requirements. From securing an allocation to receiving a Certificate of Occupancy, the total timeline is typically 3 to 5 years.

Steve Conley, Principal of the Conley Sales Group at COMPASS

Steve's Advice

Steve Conley

Principal, Conley Sales Group at COMPASS

With my contractor's license, I can tell you that building in the Keys is a long game. Even after you secure a ROGO allocation -- which can take years on its own -- you still need environmental permits from the DEP and Army Corps, plus a building permit from the county. I tell buyers to plan for 3 to 5 years from lot purchase to move-in. That timeline surprises most people, but it is the reality of building in a place with strict environmental protections and limited building allocations.

More Questions

More questions in New Construction

Ready to Take the Next Step?


We are committed to compliance with all federal, state, and local fair housing laws. We do not discriminate against any person because of race, color, religion, sex, national origin, familial status, or disability. Equal Housing Opportunity.

Equal Housing Opportunity REALTOR